Client: Vision Contracting Contract Value: €500k Project description Vision Contracting were appointed to deliver a Site Separation Facility on a large pharmaceutical development in Ringaskiddy, Co...
09/03/2017
Client:  BAM Joint Venture Contract Value:  €500,000 Project Description BAM Dragados Joint Venture have been appointed by Transport Infrastructure Ireland to design, build, finance, operate and ...
09/03/2017
Client: Goldwind Contract Value: Project Description The Gullen Range Solar Farm is a 10 – 11 MW solar photovoltaic (PV) power plant, within the existing Gullen Range Wind Farm, located 28kms north...
19/10/2016
Client: Private Developer Contract Value: $65K Project Description This project involved the demolition of two-storey and three-storey residential buildings primarily constructed of brick, blockwork ...
19/10/2016
Client:  PJ Hegarty & Sons Contract Value:  €50,000 Project Description Monford Construction Ireland Ltd are currently undertaking the in-situ concrete works for AbbVie, a pharmaceutical m...
19/10/2016
Client:  PJ Hegarty & Sons Contract Value:  €180,000 Project Description MSD Carlow is a state-of-the-art, 200,000 sq ft biologics operation facility. Monford were contracted to undertake wor...
01/04/2016
Client: CPB Contractors Contract: value $3m Project description As part of the Mitchell Freeway extension project (Burns Beach Road to Hester Avenue), CPB Contractors engaged Monford to supply and in...