- Client: Monadelphous
- Contract: value $3m
Project description
As part of Rio Tinto’s Western Turner Brockman project, Monford completed concrete, reinforcement and earthworks for a run of mine (ROM) pad. As the works were integral to the mine infrastructure program, Monford worked to strict timeframes.
Scope of work
- Supply and install formwork for slabs including scaffolding (140m2 )
- Supply and install concrete (55m3 ), reinforcement (10t) for a barrier wall
- Construct ventilation fan footings and install reinforcement and concrete
- Install hold-down bolts
- Excavate pits (320m3 ) and install concrete slabs for lighting poles (33m3 )
- Backfill and compact fill materials in compliance with specifications (550m3 )
- Install blinding concrete as per specifications
- Supply and install isolation joints and wall joints
- Install 12 bollards